Vanggatfontein project (formerly known as the Delmas project)

The Vanggatfontein Project, located some 80km east of Johannesburg on the edge of the Central Witbank Coalfield in Mpumalanga, covers an area of 1 635 hectares. In May 2009 a SAMREC-compliant coal reserve of 25.9Mt and coal resource of 163Mt was declared, and in June 2009 the Department of Mineral Resources (DMR) awarded a 20-year mining right. The initial coal reserve, which will result in a 10-year mine life, contains 3.4Mt of high-quality metallurgical coal (No 5 Seam: 1.8Mt opencast; 1.6Mt underground) and 22.5Mt of power station coal (Nos 2 and 4 Seams).

Phase 1 of Vanggatfontein’s two-phase development programme will involve development of a No 5 Seam metallurgical coal mining and processing operation, timed to benefit from a strengthening in the domestic market for high-quality metallurgical coal.

In November 2009, the Keaton Energy board gave the go-ahead for Phase 1 of Vanggatfontein’s development at a cost of R158 million, before surface rights acquisitions. SNC Lavalin South Africa is the managing contractor on the project, with DRA Mineral Projects responsible for plant design and construction and Epoch Resources for residue facility design. Minopex is the preferred plant operator and Megacube Mining, a subsidiary of Sentula Mining, the preferred opencast mining contractor.

Plant fabrication began in January 2010; the mining right became effective in February 2010; and after the amicable settlement of a land access dispute in June 2010, earthworks were able to get underway. Steel erection began in August 2010. First coal is expected in October 2010, followed by a production ramp-up to 50ktpm (ROM).

Gross In-Situ Tonnage and Mineable In-Situ Tonnage (May 2009) (Air dried basis)
 Tonnage GTISGeological lossTonnage MTISCategory
Resource area(‘000 t)(%)(‘000 t) 
Bituminous
No. 5 Seam – West1 995151 696Measured
– Middle5 413154 601Measured
– East43115366Measured
No. 5 Seam Bituminous7 839156 663Measured
No. 4 Seam – Middle45 2921040 763Measured
– East3 584103 226Measured
– West31 2951028 165Measured
No. 4 Seam Bituminous80 1711072 154Measured
No. 2 Seam – Middle38 1051034 294Measured
– East2 545102 290Measured
– West4 460104 014Measured
No. 2 Seam Bituminous45 1101040 599Measured
Subtotal Bitumious133 12010119 416Measured
Low Volatile
No. 4 Seam – Middle5 441154 625Measured
– East1 260151 071Measured
– West19 4601516 541Measured
No. 4 Seam Low Volatile26 1611522 237Measured
No. 2 Seam – Middle8 633157 338Measured
– East23415199Measured
– West16 7581514 244Measured
No. 2 Seam Low Volatile25 6251521 781Measured
Subtotal Low Volatile51 7861544 018Measured
Total Delmas Project area184 906 163 434 

Note: Coal Resources are reported inclusive of the Coal Reserves

Coal Reserve Statement (May 2009)
Mining method Coal typeProved Coal Reserves Millions of tonnes(AR)Probable Coal Reserves Millions of tonnes(AR)Total Coal Reserves Millions of tonnes(AR)Total Marke- table Coal Reserves Millions of tonnes(AR)ASH (per- cent)VM (per- cent)S (per- cent)CV (MJ/ kilogram)
OpencastPower station22.5 22.515.728.520.11.020.5
OpencastMetallurgical1.8 1.80.915.028.80.826.5
UndergroundMetallurgical 1.61.60.715.027.50.826.6
Total 24.31.625.917.3    